SCHAFBERG BATH VIENNA

As part of a comprehensive energy optimisation project, GWT’s electrical division carried out the complete replacement and construction of new switchgear for one of Vienna’s largest outdoor swimming pools. The installation of state-of-the-art control technology and precise integration of energy and consumption data raised the technical infrastructure of the 70,000 m² site to a new level of efficiency and operational reliability.

Key facts

Location

Vienna (18th district)

Services

Electrical design (ECSCAD), control panel construction, energy optimisation, dismantling & new installation

Connected load

320 kW

Scope

Main distribution board, 3-panel switchgear, sub-distribution boards & 23 frequency converters

Systems, PLC control, server visualisation, central data monitoring (electricity/water/heating)